Latest News

December 22: Update Water Pipe Replacement Linkwood Road

The crew is moving forward up Linkwood today and approaching the alley just before Ridgemede Condos. Tuesday 23rd and Wednesday the 24th the crew will be working in front of Ridgemede Condos. They will only be working a half day on Wednesday returning to work on Monday the 29th.

Just wanted to alert everyone also that there is a very little bit of water seeping from the East side of the  trench wall where they are presently working in front of the Passano residence near the two lions entrance. I have been assured by the DPW Supervisor that it is not a problem. They will be keeping an eye on the location (as I will also) for any signs of deterioration. DPW Supervisor Mark Reshnet has also bern notified.
Jack Boyson
TCNA Board Member