January 21: Updates Stony Run Lane
January 21: Updates Stony Run Lane The crew continues to lay pipe on the right (East) side of the parking loop at the Gardens of Guilford. Because of the need…
January 21: Updates Stony Run Lane The crew continues to lay pipe on the right (East) side of the parking loop at the Gardens of Guilford. Because of the need…
January 19-23: Stony Run Lane Monday the 19th the crew will NOT be working on MLKing Holiday. They will start up again early on Tuesday the 20th working their way around the right side…
January 14: Stony Run Lane by Gardens of Guilford It looks like the crew will be able to complete laying pipe under the 5ft high drain by the end of…
Updates January 13 – 15: Gardens of Guilford Alert Tuesday January 13, the crew expects to start work excavating under the 5 ft high drain that crosses Stony Run Lane…
January 12 Update: Water Replacement Project: Stony Run Lane The crew is moving up Stony Run Lane steadily, but has encountered several impediments (pipe line, gas line, electrical cable for…
January 9 Updates: Replacement Pipes Stony Run Lane The crew has been digging 8 test sites on Stony Run Lane up to and including the right hand loop of the…
January 8 Update: Linkwood Road- “Tie-In” to the new water pipes still needs to be done in the future. The crew will finished laying the last pipe as planned on…
January 7 Updates: Pipe Replacement Works Starts January 8 on Stony Run Lane Thursday the crew will be starting to lay pipe at the intersection of Stoneyford and moving up…
January 5, 2026 Updates: Linkwood Road Work Continues January 6 –Work will continue on Linkwood to the middle of the street at the corner of Linkwood and Ridgemede. The installation…
January 5 and 6: Water Pipe Replacements Continue- Linkwood Road Monday the 5th and Tuesday the 6th, crew will continue to work on the installation of the pipeline on Linkwood…