Repaving Updates for July 27
Repaving Updates for July 27 On Monday, work will start immediately at the bottom of Stony Run Lane at Stoneyford and go toward 39th Street. 1. Parking on Stoneyford…
Repaving Updates for July 27 On Monday, work will start immediately at the bottom of Stony Run Lane at Stoneyford and go toward 39th Street. 1. Parking on Stoneyford…
July 24: Repaving – Intersection at Stoneyford and Stony Run Lane will be closed. That means no traffic will be allowed through that intersection. Anyone parked on Stony Run…
UPDATES for July 23: Work will be on Stoneyford between Stony Run Lane and Linkwood. 1. Stoneyford Road (entire) NO PARKING – Cars will be towed if not moved…
Updates July 22nd: Road Repaving Calvert Lower School: Vehicles will be able to transit Tuscany Road East and West freely all day but not turn and go West on Stoneyford….
Updates for July 21st: Repaving Projects: This is the information that TCNA received at 3PM on July 20th. This information may need to change based on what happens during the…
Week of July 20, Monday the 20th, the crew will begin excavating and laying concrete on Tuscany Road starting at about the 200 block of Tuscany Road just east of the…
Updates for July 17th: Repaying Linkwood Road The work location will be from the entrance to Tuscan Hills Apts 4000-4014 Linkwood and along side of Ridgemede Apts all the…
Updates for July 16th: Repaving Linkwood Road The crew will be working from the alley just past the residence at 3925 Linkwood and Tuscan Hills Apts and next to…
Updates for July 15th: Repaving Linkwood Road The crew will continue pavement cutting, excavating, and pouring concrete on Linkwood. They will be working from approximately from the residence at…
Updates July 14: Repaving Linkwood Road The crew will continue excavating and laying concrete over the new water pipeline on Linkwood. The crew will continue where they left off about…