Calvert School just sent TCNA this latest information.
The first part of the building project is to move some of the underground utility lines in the back of the lower school building. That work may start this week. It will likely take the majority of March.
Rough outline of project with some projected timeframes
- Grading and foundation work – End of March – Mid May
- Setting the structural steel – Mid May
- Pouring the second floor slab – Late May
- Framing the exterior – Late May/Early June
- Exterior work – June and July
|