April 8: Updates, Tuscany Road Pipe Replacements
The crew was able to lay 100 ft of pipe today, or about a third of the length of the proposed pipe replacement length.
April 9: Thursday they expect to lay another 100 ft if they encounter no impediments. The crew will begin putting up traffic barrels in the middle of Tuscany Road around 8:40 PM each day. While working, there will always be one lane open to transit the work area.
Of course any vehicle parking overnight on Tuscany Road between Stoneyford and Ridgemede must be moved no later than 8 AM. Better if no one parks there overnight.
Stoneyford will be totally blocked tomorrow and Thursday during the work day as well as the same time for the rest of the week from the corner with Tuscany to the driveway down to the TLCC garages.
The crew will be storing their equipment overnight at this location for the rest of the week and also using Stoneyford as a staging area for their gravel and pipes etc. each day. No vehicles should be parking any time for the next few days in this location.