Latest News

November 26: Today they are cutting pavement toward the Tuscany beyond the white markings located on the right side sidewalk and before the entrance to the Lombardy Complex.

The superintendent of the crew will not be working after all on Thanksgiving  or Friday as originally planned.

Starting  Monday, December 1:  Work will continue only on Stoneyford though out the week until they reach Tuscany Road. Depending on progress on November 26, next week vehicles will need to be removed from before the entrance to the Lombardy complex up on Stoneyford toward the Tuscany.

December 1:The crew will work from the present pile of dirt in the street and white marking on the right side pavement on Stoneyford all the way up toward the stop sign at the corner of Stoneyford and Tuscany Road. Excavation bucket loaders, pipe delivery trucks, and dump trucks coming and going in both directions.
December 2:   Work will be in the middle of Tuscany at the corner with Stoneyford to link the pipes of both streets together. Because of the use of heavy equipment to dig up the area around the water pipe junction, there may be delays on the Tuscany Road especially during the day and in the afternoon.