Phase 1: Purple in progress, Stoneyford and Linkwood
Phase 2: Green ready to start, Stony Run Lane
Phase 3: red (not shaded) Linkwood Road from Stoneyford to Ridgemede
December 4: Water Pipe Replacement Updates
Phase 1 now completed and starting on phase 2. Work for phase 2 is scheduled to start with test pitting and saw cutting along Stony Run Lane toward the Gardens of Guilford and north of Stoneyford highlighted in green on the map. Once this section is finished, the contractor will finish phase 2 headed toward 39th street.
No Parking has been posted from Stoneyford up Stoney Run Lane toward the apartments. The contractors are waiting for an updated Ms. Utility ticket. If they receive that today (Dec 4), they will start test pitting and saw cutting tomorrow (Dec 5), if not it would be Monday December 8th
More information about if parking can be permitted on December 5 will be available soon
I appreciate all your patience while we get these upgrades made to the water infrastructure in the Stoney Run area. We will do our best to limit any inconvenience while water main replacement work is ongoing.
Mark J. Reshnet, Construction Project Supervisor I
Department of Public Works