December 5: Replacement Water Pipes for Week of December 8
Water Pipes Replacement Project: Week of December 8, Linkwood Road Starting December 8, work will begin at the corner of Linkwood and Stoneyford moving north on Linkwood instead of Stony…
Water Pipes Replacement Project: Week of December 8, Linkwood Road Starting December 8, work will begin at the corner of Linkwood and Stoneyford moving north on Linkwood instead of Stony…
Map of phases of the pipe replacement project December 5: Updates about pipe replacement plans for December 5 I just talked with superintendent Kenny and crew boss Edgar together. They…
Phase 1: Purple in progress, Stoneyford and Linkwood Phase 2: Green ready to start, Stony Run Lane Phase 3: red (not shaded) Linkwood Road from Stoneyford to Ridgemede December 4:…
December 4: Pipeline work will continue on Stoneyford until it reaches no further than the corner of Tuscany Road. The work will not extend on to the middle of Tuscany Road….
December 1: Water Pipes and Gas Work on Stoneyford What a day! Not only is work on the pipeline continuing on Stoneyford in front the Lombardy, but BGE just showed…
November 28: Gas Leak Stoneyford Road A neighbor just reported a gas leak and BGE has been called. An BGE emergency gas leak truck is on site and cones have…
November 26: Today they are cutting pavement toward the Tuscany beyond the white markings located on the right side sidewalk and before the entrance to the Lombardy Complex. The superintendent…
November 25: The superintendent of the water pipe installation project said that the crew will be working up from the corner of Stoneyford and Stony Run Lane to the white…
LATEST INFORMATION 2:00 PM, NOVEMBER 24 The supervisor of the project said that all vehicles need to be removed from Stoneyford on February 25 – including the five parking…
UPDATE PIPE REPLACEMENT PROJECT November 21, 2025: Civic Construction expect to have pipe laid to the porta potty on Stonyford. Week of November 2: Work will happen all week including…